  Construction Updates as of January 5, 2008


Amara Phase 1
Land Development

  • Balance of Works:
    Rectification works based on the punchlist  by the Project Team are completed
  • Amara Landscaping
    Softscape and Hardscape are both 100% completed.  Trees and ground covers are now evident

Amara Phase 2 Land Development

On-going works:

  • Drainage System
  • Sewer System
  • Base Preparations
  • Retaining Wall
  • Perimeter Fence

:: View Project Updates 01-05-2008 photos

 