As of February 25, 2009

AMARA - PHASE 1

 

  • Updates

  1. Land Development and Hardscaping Works 100% completed.
  2. Eighty five (85) lots were successfully turned over, two (2) move-ins and two (2) houses under construction.
  3. AMARA Clubhouse: Swimming pool, Beach Bar, Social and Function Rooms are available for lot owner's use.

 

AMARA - PHASE 2 (Land Development)

 

  • Updates - Eleven (11) lots were successfully turned over.  One (1) is under construction. 
  1. Serenity Park
    -          Physical Accomplishment Completed
     
  2. Sports Facilities
    -          Physical Accomplishment (Building): 99.07%
    -          The Landscaping (Hardscape and Softscape) works will be completed on March 30, 2009

 

AMARA - PHASE 3A (Land Development)

             

  • Updates/Activities 
  1. On-going works for the drainage, sewer and water lines.
  2. On-going base preparation at Road 13, portion of Road 1 and concrete pouring at pavement of Road 10,9 & portion of Road 1.

 

AMARA - North Tranche 1 (Land Development)

 

  • Updates/Activities
  1. Guardhouse: 86.41% Completed        
  2. On going works on access road from AMARA North guard house.

For photos, please click  gallery link: Project Updates 02-25-2009

 
 Posted: Wednesday, Feb 25, 2009

 