  Construction Updates


Amara - Phase 1

  1. Land Development and Hardscaping Works 100% completed.
  2. Administration office at the Clubhouse is fully functional. A Technical Assistant is on duty to attend to lot owners technical concerns.
  3. Amara Clubhouse : Swimming pool, Beach Bar, Social and Function Rooms are available for lot owner's use.
  4. Eighty nine (89) lots were successfully turned over to lot owners, three (3) move-ins and two (2) houses under construction as of June 15, 2009.

Amara - Phase 2

  • Updates
    • Thirty Seven (37) lots were succcessfully turned over to lot owners. One (1) is under construction as of June 15, 2009.
    • Ongoing works on planting strips and landscaping
  1. Serenity Park
    - Trees and Ground Covers are very evident
    - Ongoing works on some area
  2. Sports Facilities
    - Physical Accomplishment (building : Basketball, Badminton & Fitness Gym) : 99.07 %
    - Ongoing landscaping and finishing works

Amara - Phase 3A

  • Updates / Activities
    Ongoing works on the following :
    1. Drainage, sewer and water lines.
    2. Base Preparation at Road 13, portion of Road 1.
    3. Concrete pouring ar Road Pavement.

Amara - North Tranche 1 (Land Development)

  • Updates / Activities
    1. Access Road - Completed
    2. Guardhouse : 96.13 completed
    3. Ongoing rearthworks and clearing and grubbing.

For photos, please click gallery link : Project Updates 05-25-2009

 
 Posted: Monday, May 25, 2009

 